Flatiron Energy is proposing a large Brighton battery storage plant, called Streetcar Storage, along Soldiers Field Road, with up to 300 megawatts of output and 1,200 megawatt-hours of storage, according to the project website the company has posted, as reviewed Wednesday, Nov. 25.[1] The Boulder, Colorado, company dropped plans for a smaller plant on nearby Electric Avenue last year, Universal Hub reported Monday, Nov. 23.[2]
What is proposed
Streetcar Storage is a battery energy storage system that would take electricity from the grid, hold it, and send it back when demand is high.[1] The developer lists a maximum power output of 300 MW and a maximum storage capacity of 1,200 MWh, which it says is enough energy to power around 60,000 Massachusetts households for one month.
[1] At full output, that capacity would last about four hours (TBR calculation).
The plant would connect to the grid at Eversource’s Electric Avenue 115 kV substation.[1] The earlier Electric Avenue plan, which Flatiron called Project Lite Brite, would have used the same substation and had a maximum output of 185 MW.[2]
Where it would go
The project website names Soldiers Field Road in Brighton but gives no street address.[1] Allston Civic Association President Anthony D’Isidoro told a neighborhood email list that, as he understands it, the site is 1660-1670 Soldiers Field Road (3.45 acres) and 1800 Soldiers Field Road (1.06 acres).[3] Together that is about 4.5 acres (TBR calculation).
Those parcels hold the Charles River Motel and a two-story office and retail building, with a McDonald’s between them, and sit just across the Massachusetts Turnpike from the abandoned Electric Avenue site.[2] In 2023, a Dallas developer and a Boston housing nonprofit floated a plan for offices and 200 affordable apartments on that land plus the IHOP parcel, but never filed formal plans with the city.[2]
Who decides, and when
The project needs approval from the state Energy Facilities Siting Board to be built and run, and the developer says that review will include public meetings and comment periods.[1] A 2024 state law moved oversight of large clean energy facilities to the state; the Boston Planning Department can make recommendations but does not have the final say.[2] D’Isidoro wrote that the city will have a limited right to intervene and that the formal state process is scheduled to begin in mid-February.[3]
No community meeting date has been posted. As of Wednesday, the project’s permitting section said there were no notices or updates at this time.[1] Flatiron’s posted schedule shows permitting starting in the fourth quarter of 2026, construction in the third quarter of 2028 and commercial operation in the fourth quarter of 2029.[1]
What the developer promises, and what neighbors raised before
Flatiron says construction would generate about $16.4 million in local earnings and around 100 local jobs, and that it will sign a Host Community Agreement with the City of Boston.[1] The company says battery storage helps the grid absorb solar and wind power and reduces reliance on older fossil-fuel plants that run during demand peaks.[1]
When Flatiron withdrew the Electric Avenue plan, it cited uncertainty over proposed state safety rules for large battery buildings.[2] Residents near that site, some in homes about 40 feet from the proposed building, had raised concerns about what a fire there could do.[2]
For more on local development and energy, see our coverage of temporary music and art studios planned at 290 North Beacon in Brighton, the Jackson Mann community center and housing plan in Allston and Powertown’s battery network for Brockton businesses. More coverage is on our Boston Local News page.
Sources
- Flatiron Energy (developer project site): Streetcar Storage: Energy Storage Facility, Brighton, Massachusetts
- Universal Hub: Large electricity storage plant could land on Soldiers Field Road in Brighton
- AllstonBrighton2006 community email list: Streetcar Storage post by Anthony D’Isidoro
Read next in Boston Local News
Boston Local NewsHealey Awards $20 Million in Winter Storm Hardship Grants to 32 Massachusetts Communities
Boston Local NewsJudge Says Plymouth Can’t Demand Insurance for the Day of Mourning, but the Town Doesn’t Have to Build the Stage
Boston Local NewsWegmans in Burlington: How a 1916 Rochester Produce Business Became America’s No. 1 Retail Workplace
Most read this week
- Strait of Hormuz Insurance Rates Explained: What War-Risk Cover Costs in 2026
- Notre Dame Drops to No. 6 After Routing Boston College as Georgia Stays No. 1 in CFP Rankings
- MIT Checks a Claimed Riemann Hypothesis Proof as 175,187 Lean Files Compile Without Errors
- Boston Thanksgiving Traffic Could More Than Double. AAA Says Leave Before Noon Wednesday
- What’s Open in Boston on Thanksgiving: Market Basket Closed, Walgreens Open, Free Meals at 11 a.m.
Latest
- Leaked Rosstat Data Shows at Least 490,000 Russian Soldiers Killed in Ukraine, BBC and Mediazona Report
- U.S. Probes Iran Ties to Hacks of Up to 50 Commercial Ships, Including an LNG Tanker
- China’s Shenzhou-24 Carries Pakistan’s Muhammad Zeeshan Ali, the First Foreign Astronaut to Tiangong
- Africa Cup of Nations Title Returned to Senegal as Sports Court Overturns Morocco Forfeit Win
- Montserrat College of Art Now Guarantees Every New Student a Paid Job at $15 an Hour
Get The Boston Report Briefing
Our free weekly email with the most important stories from Boston and the world. Unsubscribe anytime.
Free. We never sell your address. Privacy policy